Insulation resistance measurements should be taken from winding to winding and winding to ground for the duration of at least ___________.

Prepare for the AVO Substation Maintenance II Test. Use flashcards and multiple choice questions, each with hints and explanations. Ace your exam with confidence!

Insulation resistance measurements are crucial for assessing the integrity of electrical insulation within equipment like transformers and generators. Taking these measurements involves applying a test voltage and waiting for the insulation resistance value to stabilize.

The recommended duration for these tests is at least 10 minutes. This duration is important because it allows enough time for moisture or other contaminants in the insulation material to dissipate and for the readings to stabilize, reflecting a more accurate condition of the insulation. Shorter test durations might not provide reliable or consistent results, as they could reflect transient conditions rather than the true insulation status.

By conducting the insulation resistance test for 10 minutes, technicians can ensure that they obtain a reading that genuinely indicates the insulation's performance and condition, which is essential for identifying potential failures that could lead to equipment damage or operational issues. Therefore, the correct answer reflects the industry standard for the duration of insulation resistance measurements.